Why waterproofing comes first in a bathroom renovation
In a bathroom renovation, everyone talks about tiles and fittings. But what decides how long the bathroom lasts is the waterproofing under the tiles.
The right order: strip-out, plumbing, pressure test, screed and falls, waterproofing, flood test and finally tiling. Skipping a step means costs on your ceiling and your neighbour's a few years later.
Planning a bathroom renovation? We can assess the current state together during a free site survey.
- 01
Tiles let water through
Grout lines and even tiles do not fully hold water back. The real protection is the waterproofing layer underneath.
- 02
Leaks go downstairs
An unsealed shower shows up later as stains, blistering and mould on the ceiling below. Fixing it means breaking the new tiles.
- 03
The right order
Strip-out → new plumbing → pressure test → screed and falls → waterproofing → flood test → tiling.
- 04
Corners and shower area
Use sealing tape at wall-floor joints, and waterproof shower walls at least up to shower-head height.
- 05
Test before you close
After waterproofing, fill the floor with water and wait a day. A simple but valuable check. Tiles go down after that.